Project Upgrade Delays

Minor · Started Aug 3, 2026 · 3:28 PM

  • Duration

    2d 2h 5m

  • Severity

    Minor

  • Detection lead

  • User reports

Summary

Project Upgrade Delays

Project upgrades have remained stable, we are resolving this incident.


  • Started

    Aug 3, 2026 · 3:28 PM

  • Resolved

    Aug 5, 2026 · 5:33 PM

  • Duration

    2d 2h 5m

  • Severity

    Minor

Event timeline

How this incident unfolded

  • Investigating

    Aug 3 · 3:28 PM Supabase

    We are investigating a potential issue that could result in a delay or failure in some users' project upgrades.

  • Investigating

    Aug 3 · 4:19 PM Supabase

    We are continuing to investigate project upgrade issues.

  • Identified

    Aug 3 · 5:09 PM Supabase

    We have identified the cause of the upgrade delays and are working on a fix.

  • Identified

    Aug 3 · 7:47 PM Supabase

    We are developing a fix for the upgrade issues.

  • Identified

    Aug 3 · 10:46 PM Supabase

    We are continuing to fix project upgrade issues and are investigating further remediation. We will provide our next update within the next 14 hours.

  • Identified

    Aug 4 · 3:30 PM Supabase

    The team has identified a likely fix and is consolidating the details in order to move to thorough testing. We will update again when the fix is applied.

  • Identified

    Aug 4 · 11:38 PM Supabase

    We are continuing to test the fix to project upgrades. We will update again when the fix is applied.

  • Monitoring

    Aug 5 · 2:58 PM Supabase

    We have deployed a tested fix for the upgrade issue impacting some projects. The fix has been effective and we are monitoring for continued stability.

  • Resolved

    Aug 5 · 5:33 PM Supabase

    Project upgrades have remained stable, we are resolving this incident.