Linode Status · History · Incident #153554

RESOLVED

Connectivity Issue between ID-CGK (Jakarta) and SG-SIN-2 (Singapore 2)

Minor · Started Oct 25, 2026 · 1:54 PM

  • Duration

    22d 4h 5m

  • Severity

    Minor

  • Detection lead

    —

  • User reports

    —

Summary

Connectivity Issue between ID-CGK (Jakarta) and SG-SIN-2 (Singapore 2)

Starting around 07:00 UTC on October 24, 2026, an issue affecting connectivity between our ID-CGK \(Jakarta\) and SG-SIN-2 \(Singapore 2\) was identified. The investigation revealed that the issue was caused by an undersea cable cut affecting the international link capacity, which would have resulted in connection timeouts and/or errors for services deployed in these data centers. To mitigate the immediate impact while the undersea cable was being repaired, we removed the affected links from production traffic and limited the link capacity; network stability was restored following these actions. The impact was fully mitigated at 17:50 UTC on November 13, 2026, once the undersea cable repairs were finished and all previous changes were reverted. We apologize for the impact and thank you for your patience and continued support. If you have further questions, please contact us at 855-454-6633 \(\+1-609-380-7100 Intl.\), or send an email to [support@linode.com](mailto:support@linode.com) for assistance. This summary provides an overview of our current understanding of the incident given the information available. Our investigation is ongoing, and any information herein is subject to change.


  • Started

    Oct 25, 2026 · 1:54 PM

  • Resolved

    Nov 16, 2026 · 6:00 PM

  • Duration

    22d 4h 5m

  • Severity

    Minor

Event timeline

How this incident unfolded

  • ◐

    Investigating

    Oct 25 · 1:54 PM Linode

    Our team is investigating an issue affecting connectivity between our ID-CGK (Jakarta) and SG-SIN-2 (Singapore 2) data centers. During this time, users may experience intermittent connection timeouts and errors for all services deployed in this data center. We will share additional updates as we have more information.

  • ◐

    Investigating

    Oct 25 · 2:52 PM Linode

    We are continuing to investigate this issue. We will share additional updates as we have more information.

  • ◉

    Monitoring

    Oct 25 · 4:12 PM Linode

    At this time, we have been able to correct the issues affecting connectivity between our ID-CGK (Jakarta) and SG-SIN-2 (Singapore 2) data centers. We will be monitoring this to ensure that it remains stable. If you are still experiencing issues, please <a href="https://cloud.linode.com/support/tickets">open a Support ticket</a> for assistance.

  • ◉

    Monitoring

    Oct 25 · 4:13 PM Linode

    We are continuing to monitor for any further issues.

  • ◉

    Monitoring

    Oct 29 · 9:16 AM Linode

    We will continue to monitor to ensure that the impact has been fully mitigated. Further updates will be provided as we make progress.

  • ✓

    Resolved

    Nov 16 · 6:00 PM Linode

    We haven’t observed any additional connectivity issues in our ID-CGK (Jakarta) and SG-SIN-2 (Singapore 2) data centers, and will now consider this incident resolved. If you continue to experience problems, please <a href="https://cloud.linode.com/support/tickets">open a Support ticket</a> for assistance.

  • ✓

    Postmortem

    Nov 19 · 1:58 PM Linode

    Starting around 07:00 UTC on October 24, 2026, an issue affecting connectivity between our ID-CGK \(Jakarta\) and SG-SIN-2 \(Singapore 2\) was identified. The investigation revealed that the issue was caused by an undersea cable cut affecting the international link capacity, which would have resulted in connection timeouts and/or errors for services deployed in these data centers. To mitigate the immediate impact while the undersea cable was being repaired, we removed the affected links from production traffic and limited the link capacity; network stability was restored following these actions. The impact was fully mitigated at 17:50 UTC on November 13, 2026, once the undersea cable repairs were finished and all previous changes were reverted. We apologize for the impact and thank you for your patience and continued support. If you have further questions, please contact us at 855-454-6633 \(\+1-609-380-7100 Intl.\), or send an email to [support@linode.com](mailto:support@linode.com) for assistance. This summary provides an overview of our current understanding of the incident given the information available. Our investigation is ongoing, and any information herein is subject to change.

Get an email when Linode opens, updates or resolves an incident.

Add it as a dependency monitor. The Free plan includes one.